Question 1 / 27
財務與會計基礎
Question 1
All companies must provide several key financial statements. Which of the following is NOT a mandatory core financial statement?
- A. Statement of comprehensive income
- B. Statement of financial position
- C. Internal management budget report
- D. Cash flow statement
✅ 答案解析
強制性財務報表包括綜合收益表、財務狀況表、現金流量表等,用於對外披露。內部管理預算報告僅供內部決策,不屬於強制披露的核心財務報表。
財務與會計基礎
Question 2
What is the core difference between management accounts and financial accounts?
- A. Management accounts are for internal decision-making, while financial accounts are for external stakeholders
- B. Financial accounts are more detailed than management accounts
- C. Management accounts are audited, while financial accounts are not
- D. They have no essential differences, just different naming conventions
✅ 答案解析
核心區分在使用對象:管理會計面向內部管理層,支持決策;財務會計面向外部利益相關者(投資者、監管機構),需遵循會計準則。
財務與會計基礎
Question 3
The statement of comprehensive income mainly reflects a company's ______, while the statement of financial position focuses on its ______.
- A. asset structure; profit and loss over a period
- B. profit and loss over a period; asset and liability status at a specific point
- C. cash flow; equity changes
- D. equity changes; cash flow
✅ 答案解析
綜合收益表是期間報表,反映一段時間損益;財務狀況表是時點報表,反映特定日期資產負債狀況,二者功能明確區分。
財務與會計基礎
Question 4
Which of the following items is typically included in the statement of financial position?
- A. Annual sales revenue
- B. Operating expenses in the current period
- C. Accounts receivable and payable
- D. Depreciation expense of fixed assets
✅ 答案解析
財務狀況表列示資產、負債、所有者權益:應收賬款(流動資產)、應付賬款(流動負債)屬於其核心項目,其餘選項為損益表項目。
財務與會計基礎
Question 5
The main purpose of preparing financial accounts for a construction company is to ______.
- A. assist project managers in adjusting construction schedules
- B. provide transparent financial information for investors and regulatory authorities
- C. calculate the bonus of project teams
- D. formulate the next year's project bidding plan
✅ 答案解析
財務會計的核心目的是向外部利益相關者提供真實透明的財務信息,協助其做出投資、監管等決策,其餘選項為管理會計功能。
職業道德與客戶服務
Question 6
If you are a contractor QS and your boss asks you to claim for items not entitled under the contract, your most appropriate response is to ______.
- A. comply immediately to maintain the boss's trust
- B. refuse firmly and explain the contractual risks and professional ethics requirements
- C. find a loophole to make the claim appear legitimate
- D. pass the task to a colleague to avoid responsibility
✅ 答案解析
根據RICS職業道德準則,QS需堅持誠信,拒絕違反合同的索賠要求,並向老闆說明法律風險,避免違規和聲譽損失。
職業道德與客戶服務
Question 7
According to RICS ethical standards, can a QS accept red pockets or gifts from contractors?
- A. Yes, as long as the value is small
- B. No, in any case, to avoid conflicts of interest
- C. Yes, if it is a festival gift without specific purpose
- D. It depends on the company's internal regulations, regardless of RICS requirements
✅ 答案解析
RICS準則禁止QS接受任何可能影響獨立判斷的禮物/紅包,無論價值大小,核心是避免利益衝突,維護職業公正性。
職業道德與客戶服務
Question 8
Which of the following behaviors best reflects the integrity of a QS?
- A. Concealing minor errors in the engineering quantity calculation to avoid rework
- B. Disclosing all relevant contract information to both the employer and contractor fairly
- C. Prioritizing the employer's interests even if it violates the contract terms
- D. Accepting hidden commissions from suppliers to reduce project costs
✅ 答案解析
誠信(Integrity)的核心是公正透明:公平向雙方披露合同信息,不偏袒、不隱瞞,符合RICS職業道德的核心要求。
職業道德與客戶服務
Question 9
What is the key to providing high-standard QS professional services?
- A. Completing tasks as quickly as possible regardless of accuracy
- B. Mastering professional knowledge and maintaining effective communication with all stakeholders
- C. Minimizing communication with contractors to avoid disputes
- D. Only following the employer's instructions without independent judgment
✅ 答案解析
高標準服務的核心是:1. 紮實的專業知識(成本、合同、法規);2. 與各方的有效溝通,避免誤解,推動項目順利進行。
職業道德與客戶服務
Question 10
Which of the following is a necessary component of an organization's complaints handling procedure?
- A. A fixed complaint acceptance window (only working hours on weekdays)
- B. Clear steps for complaint verification, handling, and feedback
- C. The right to reject complaints without providing reasons
- D. Transferring all complaints to external institutions for handling
✅ 答案解析
有效的投訴處理流程需具備驗證、處理、反饋的清晰步驟,確保投訴得到公正解決,提升客戶滿意度,其餘選項不符合服務原則。
職業道德與客戶服務
Question 11
To promote trust in the QS profession, the most effective measure is to ______.
- A. Advertise widely on public platforms
- B. Ensure all professional behaviors are compliant with industry standards and transparent
- C. Lower service fees to attract more clients
- D. Cooperate only with large enterprises and institutions
✅ 答案解析
行業信任來源於規範性和透明度:QS嚴格遵守RICS標準和合同要求,行為公開透明,才能獲得客戶和社會的真正信任。
職業道德與客戶服務
Question 12
When encountering a client with unreasonable demands, a QS should first ______.
- A. Refuse directly to avoid subsequent troubles
- B. Explain the contractual provisions and professional norms to guide the client to adjust demands
- C. Compromise to maintain the client relationship
- D. Report to the regulatory authority immediately
✅ 答案解析
面對不合理要求,首要步驟是依據合同條款和專業標準耐心解釋,引導客戶調整預期,平衡原則與客戶關係,避免極端處理方式。
職業健康與安全(OHS)
Question 13
As a QS, your OHS-related responsibility does NOT include ______.
- A. Reviewing whether the project budget includes OHS-related costs
- B. Supervising the contractor's on-site safety construction operations directly
- C. Reminding the employer to reserve funds for OHS facilities
- D. Participating in OHS risk assessment meetings for the project
✅ 答案解析
QS的OHS責任集中在成本和合同支持,直接監督現場安全是Safety Officer / Safety Supervisor的職責,非QS工作範疇。
合約管理核心
Question 14
What is the definition of "retention" in construction contracts?
- A. A portion of the project payment withheld to ensure the contractor completes defect rectification
- B. A deposit paid by the contractor to the employer to guarantee contract performance
- C. A penalty for the contractor's delay in construction
- D. A bonus for the contractor's high-quality completion of the project
✅ 答案解析
保留金(Retention)是僱主扣留的部分進度款,用於擔保承包商在缺陷責任期內完成修復,不同於履約保證金、罰金或獎金。
合約管理核心
Question 15
The key difference between a letter of intent and a letter of award is that ______.
- A. A letter of intent has legal binding force, while a letter of award does not
- B. A letter of award is a formal notice of contract award, while a letter of intent is a preliminary intent confirmation without full binding force
- C. A letter of intent is issued by the contractor, while a letter of award is issued by the employer
- D. There is no essential difference between the two
✅ 答案解析
授標函(LOA)是正式授標通知,具完全法律約束力;意向書(LOI)是初步確認,僅特定事項有約束力,二者均由僱主發出。
合約管理核心
Question 16
Which of the following is NOT an essential element of a legally binding contract?
- A. Offer and acceptance
- B. Consideration (remuneration or equivalent value)
- C. Written form (no oral form is allowed)
- D. Intention to create legal relations
✅ 答案解析
書面形式並非強制要求,口頭合同在多數情況下同樣具有約束力。
合約管理核心
Question 17
The difference between express terms and implied terms of a contract is that ______.
- A. Express terms are written, while implied terms are oral
- B. Express terms are clearly stated in the contract, while implied terms are derived from law or industry practices
- C. Express terms are only applicable to large projects, while implied terms are for small projects
- D. Implied terms have higher legal effect than express terms
✅ 答案解析
明示條款是合同中明確寫明的條款;默示條款來自法律規定或行業慣例,二者均具法律效力。
合約管理核心
Question 18
The core benefit of using standard contract forms is to ______.
- A. Reduce the cost of contract drafting and avoid ambiguous clauses
- B. Increase the negotiation space between the employer and contractor
- C. Make the contract more favorable to the employer
- D. Shorten the project construction period
✅ 答案解析
標準合同的核心優勢是:降低起草成本、減少歧義條款、提供行業認可的風險分配機制。
合約管理核心
Question 19
What does "fluctuation" in construction contracts refer to?
- A. Adjustments to the contract price due to changes in material prices, labor costs, etc.
- B. Changes in the project construction scope proposed by the contractor
- C. Delays in project progress caused by force majeure
- D. Disputes between the employer and contractor over payment
✅ 答案解析
價格波動條款(Fluctuation)允許因材料價格、人工成本等市場變化調整合同價格,保護承包商免受通脹風險。
合約管理核心
Question 20
A "bond" in construction projects is mainly used to ______.
- A. Provide financial guarantee for the contractor's performance of contractual obligations
- B. As an advance payment for the contractor to purchase materials
- C. Compensate the employer for losses caused by design changes
- D. Pay for the project's OHS-related expenses
✅ 答案解析
保證金(Bond)是由銀行或保險公司出具的財務擔保,確保承包商履行合同義務,若違約僱主可索賠,不同於預付款或罰金。
合約管理核心
Question 21
When selecting the most appropriate form of contract, the first factor to consider is ______.
- A. The complexity of the project and the allocation of risks
- B. The preferences of the project manager
- C. The contract template used in previous projects of the company
- D. The lowest service fee of the legal advisor
✅ 答案解析
選擇合同形式需首先考慮項目複雜度(如規模、技術難度)和風險分配(如價格風險由誰承擔),其餘選項非核心考量因素。
合約管理核心
Question 22
Which of the following is a core element of contract documents for construction projects?
- A. The employer's internal financial budget
- B. Engineering drawings, specifications, and bill of quantities
- C. The contractor's staff resume
- D. Market research reports on building materials
✅ 答案解析
建築工程合同文件的核心要素包括工程圖紙、規格說明書、工程量清單,這些是定義工程範圍和計價的基礎,其餘選項非合同核心文件。
價值管理與變更管理
Question 23
What is the core meaning of "value for money" in QS work?
- A. Achieving the best functional effect at the lowest cost
- B. Reducing the project budget as much as possible regardless of quality
- C. Using the most expensive materials to ensure project quality
- D. Prioritizing the interests of the consulting party to obtain higher service fees
✅ 答案解析
物有所值(Value for Money)的核心是在控制成本的前提下實現最佳功能效果,而非單純追求最低價或最高品質。
價值管理與變更管理
Question 24
During the design stage, the way to implement value for money is to ______.
- A. Adopt overly conservative design schemes to avoid risks
- B. Conduct value engineering analysis to optimize the design while controlling costs
- C. Determine the design scheme only based on the designer's experience
- D. Increase the design margin to cope with subsequent changes
✅ 答案解析
設計階段實現物有所值需進行價值工程分析(Value Engineering),在滿足功能需求的前提下優化設計、控制成本,而非過度保守或依賴經驗。
價值管理與變更管理
Question 25
If a contractually valid substantial variation order (VO) needs to be paid to the subcontractor, how can a QS persuade the PM to approve the payment?
- A. Hide the relevant contract clauses and only emphasize the project progress needs
- B. Provide detailed contractual basis and cost calculation, and explain the impact of non-payment on project progress and quality
- C. Threaten to report the PM to the superior if the payment is not approved
- D. Compromise to reduce the payment amount without authorization
✅ 答案解析
處理有效的Variation Order(VO)時,QS應提供詳細的合同依據和成本計算,說明不付款對項目進度和質量的影響,以專業方式說服PM批准。
價值管理與變更管理
Question 26
During the tender stage, implementing value for money requires QS to ______.
- A. Only select the lowest bidder to reduce costs
- B. Evaluate bids comprehensively based on price, technical strength, and past performance
- C. Increase the tender deposit to screen out small contractors
- D. Shorten the tender period to speed up the project commencement
✅ 答案解析
招標階段實現物有所值需綜合評標,考慮價格、技術實力、過往業績等因素,而非單純追求最低價或設置不合理門檻。
價值管理與變更管理
Question 27
During the construction stage, the key measure to ensure value for money is to ______.
- A. Strictly control variation orders and verify the quantity and price of variations
- B. Approve all payment applications of the contractor as soon as possible
- C. Reduce the frequency of on-site inspections to save labor costs
- D. Agree to all the contractor's proposals for material substitution
✅ 答案解析
施工階段確保物有所值的關鍵是嚴格變更令管理(VO),核實變更的數量和價格,避免不必要的成本增加。